Base Module - Getting Started
This Getting Started document will guide
you through the
working process of 3f Project 2006
Base Module, which takes less than half an
hour. Once you have gone through this
paper, we strongly suggest that you take a look
at the “Advanced
Features” paper where more powerful
advantages are described.
It is assumed that you have set up a 14-day
trial account on our hosted server or that 3f Project 2006 has been installed on your own
server. If you have not yet set up the trial
account, go to
http://www.3f-project-management.com/start/
to do so.
CUSTOMIZING
Step 1. Enter employees
Click Projects & Resources > Login
Resources
|
On the "Login Resources" page click “Add
New” |
 |
and fill out the form. |
Note: Set up a new Department by
clicking Administration > Departments
Step 2. Enter clients
Click Projects & Resources > Client and
Projects
|
On the "Client and Projects" page click
“Add New” |
 |
and fill out the form. |
Note: Set up a new Project Type by
clicking Administration > Project Types
Step 3. Set up client project
Click Projects & Resources > Client and
Projects
On the “Client and Projects” page, click
“Add/View Projects” to the right of the
specific client for whom you wish to set up
a new project.
|
On the “Project List” page click “Add
New” |
 |
and fill out the form. |
Step 4. Add tasks to client
project
Click the
Tree View > Projects > Name of Client >
Name of Project > Tasks
|
On the “Task List” page click “Add
New” |
 |
and fill out the form. |
Note: Please disable your popup
blocker for the server address.
Important: An unlimited number of
persons may work on the same task at the
same time. Therefore, enter hours for the
team as a whole.
Step 5. Set Up System Defaults
(Optional)
Click Administrative > System Defaults
Define your mail server for out going
e-mails.
Define time tracking round off.
Upload images (e.g., your logo) to be used
as header on printouts and in HTML
e-mails.
TIMESHEET
6. Fill in timesheet
Click the
Tree View > My Workspace> My
Timesheet
Timesheet entries are done by choosing the
project and task then entering the start
and end time. Click Add Record to save the
timesheet item. Continue until you've made
all the entries for a particular day.
Note: If you want to submit a
timesheet for a different day you may do
so by choosing day from the date picker or
navigate using the next and previous
arrows.
7. Submit timesheet
Click the
Tree View > My Workspace > My Timesheet
> Today's Date
Before submitting your timesheet update
the Billable Hrs. and Remaining Hrs. (See
help file for information on these two
fields)
Click Submit Timesheet.
Note: If the
optional Approval Management module is
active and the project is setup not to
require timesheet approval then the
timesheet is automatically approved upon
submission. If the optional Approval
Management module is not active then
timesheets are always automatically
approved upon submission.
Step 8. Tasks Remaining Hours
Click the
Tree View > Projects > Name of Client >
Project Name >
Project Management > Tasks Remaining Hours
The person in charge of the project
accepts or corrects the remaining working
hours for each individual task as
submitted by the resources.
|
Planned Hrs: |
Original planned hours |
|
Rem. Hrs: |
Corrected remaining hours |
|
Res. Rem. Hrs: |
Estimated remaining hours as projected
by team members |
Recommendation: We suggest you
review your projects on a daily basis, as
the remaining hours are the foundation for
the Project Overview reports.
Note: To set a task to "Finished",
enter 0 in the "Rem. Hrs." (Remaining
Hours) field across the task.
REPORTS
Note: All reports
are based on submitted timesheets only.
1. Time Report
Click the
Tree View > Projects > Name of Client > Project Name >
Project Reports > Time Report
This report shows total hours worked on
the active project shown in the status bar at
the bottom of the screen.
|
Set the date range by clicking |
 |
“Date from” and |
 |
“Date to” then press the |
 |
button. |
You may filter results by “Department”
and/or “Resource” and you may use the
“Group by” option.
2. Project Overview
Click the
Tree View > Projects > Name of Client > Project Name >
Project Reports > Project Overview
This report lists all the tasks set up
within an active project.
|
Hours Planned: |
Originally planned hours |
|
Hours Actual: |
Realized working hours |
|
Hours Remaining: |
Remaining hours of a task as set by
the person in charge of the project
(see Step 13) |
|
Deviation Planned/Actual: |
Difference between planned and
realized hours
Formula: Planned - Actual |
|
Deviation Planned/Current: |
Number of hours ahead or behind
original schedule
Formula: Planned - (Actual +
Rem. Hrs) |
|
% Finished: |
The percentage finished for a task
Formula: 100 * [Actual /
(Actual + Rem. Hrs)] |
3. Project Home
Click the
Tree View > Projects > Name of Client > Project Name >
Project Management > Project Home
This is the Project Summary.
|
Plan
Hrs.: |
Original planned
hours per project phase |
|
Act.
Hrs.: |
Total realized working hours per
project phase |
|
Rem.
Hrs.: |
Best possible
estimate for remaining hours as made
by the person in charge of the project
per project phase (see Step 13) |
|
Percentage
(%): |
Percent completed
Formula: Act. Hrs / (Rem. Hrs. + Act.
Hrs.) |