Base Module - Advanced Features
It is assumed that you have set up a 14-day
trial account on our hosted server or that 3f Project 2006 has been installed on
your own server. It is furthermore assumed that you are
already familiar with the
functionality of the Base Module.
If you have not yet set up the trial
account, go to
http://www.3f-project-management.com/start/
to do so.
1. Client Requests
"Client Request" is used to record
and manage requests made by the client in
one place. Client requests are usually
tasks or additions which are not part
of the original project. Optionally, a
client request can be converted into a task.
To add a Client Request
Click the
Tree View > Projects > Name of Client >
Project Name > Client Request
|
On the “Client Request Details” page,
click the Add New icon |
 |
;
fill out the subsequent page, then click
Save. |
Note: It is important to enter the
client request in the right project. To
activate a project, click Project List >
Choose Client > Choose Project.
Convert a client request to a task
Click the
Tree View > Projects > Name of Client >
Project Name > Client Request
Click on the request that you want to convert
to a task.
|
On the “Client Request Details” page,
click the “Convert to Task” icon |
 |
|
The request is converted to a task. To
view the new task and add planned hours,
click Project > Task, then locate and click
the name of the converted task.
2.Project Templates
To save time and avoid omitting
standard project tasks, a template can be
imported into any project. During the
import process, you can choose which tasks
to import.
Templates are created from existing
projects by exporting the tasks to be
included in the template. You can create
different project templates for each type
of project you do.
To create a template
File > Export > XML - Task List
To import a template
File > Import > XML - Task List
3. Errors and Changes
The
Errors and Changes page is where you track all
issues within a project. Issues refer to
problems, questions, or corrections in a
project that must be resolved.
To enter a new Error and Change item
Click the
Tree View > Projects > Name of Client >
Project Name > Errors and Changes
|
On the “Errors and Changes” page, click
the “Add New” icon |
 |
and fill out the form. |
Note: An Errors and Changes item
can be converted to a task.
4. Project Grouping
Project Grouping provides you with an
overview of the number of hours that has
gone into a group of projects, which are
not otherwise related to each other. You
can set up an unlimited number of project
groups in which you can include an
unlimited number of projects from any
client. You can even include the same
project in multiple project groups.
To create a Project Grouping
Click the
Tree View > Projects > Project Grouping
5. Group, Copy and Rearrange Tasks in the
Task List
You can group, copy and rearrange tasks in
the task list. To learn more about
grouping, copying and rearranging of
tasks, we suggest that you view our
video tutorial:
http://www.3f-project-management.com/kb/video-tutorial/f2005/ENT_9-1_Grouprearrangeandcopytasks.html
Note: The tutorial is from a
previous version of 3f Software Planner,
thus, the look and feel is different
from the 3f Project 2006's look and feel.
However, the
general principles are the same.
Gantt Diagram
-
You can specify a work calendar for each
individual resource.
-
You can plan the project graphically
using a Gantt diagram.
-
You can plan what individual resources
should do on a given day.
-
You can view daily, weekly and monthly
plans.
-
You can create enterprise resources.
1. Work Calendar
Click the
Tree View > Administrative > Work
Calendar
To add a new calendar or edit an existing
calendar, click the Add New icon on the
loaded page.
2. Assign work calendar to a login
resource
Click the
Tree View > Resources > Login Resources
> Name of the resource
On the subsequent page, you can choose a
different work calendar or edit the one
assigned to the resource. Any change you
make will not affect any master calendar.
3. Plan using the Gantt
diagram
Click the
Tree View > Projects > Name of Client >
Project Name
> Gantt Diagram
Start entering a new task by clicking "Add
Task Here". When you have entered the task
name, click Enter on the keyboard. Navigate
to the next column using the arrow on your
key board. To activate a column for input,
press the Enter key on the keyboard. We
strongly suggest that you review the Help
files for the Gantt diagram.
Note: Any task entered in
the Gantt diagram is automatically available
in the Task List.
4. Plan resources in the Gantt
diagram
|
Assuming you are still in the Gantt
diagram, click the task for which you want to
create a resource. Next, click the link
"Click on a task," then "Click here to
open scheduling pane." |
A scheduling pane will now open below the
Gantt diagram listing all the resources
working on the project. All the days
covered by the task duration are listed
across each login resource. Enter the
number of hours you want to plan a
resource for the on a given day.
Note: When you plan a resource on a
task, the hours you plan are shown on the
resource's Today
page.
5. View work schedule -
Enterprise Level
Click the
Tree view > Enterprise > Work Schedule
On the page that loads, click the link
"Click to view" across the resource, the work schedule
of whom you want to see .
6. View work schedule -
Project Level
Click the
Tree view > Projects > Name of Client >
Project Name > Project Reports > Work
Schedule
On the page that loads, click the link
"Click to view" across the resource,
the work schedule of which you want to
see.
7. Set up enterprise resources
Click the
Tree View > Resources > Enterprise
Resources
Information: An enterprise resource
does not have a login
to the system. Enterprise resources can be
assigned to a project in the same fashion
as a regular login resource. If you do not
have the Approval Management module, all
enterprise resources in the system are
automatically assigned to any new project.
8. Setup project resources
Click the
Tree View > Resources > Enterprise
Resources
Information: A project resource does not have a login to
the system and which can only be used
within the project where it was added.
If you do not have the Approval Management
module, all project resources in the
system are automatically assigned to any
new project.
Information about enterprise and
project resources: Enterprise
and project resources are typically used
when you want to schedule objects like
cars, meeting rooms, equipment, etc for
particular projects. They
can also be used if you have third party
consultants who work on projects from time
to time. The system allows you to set up an
unlimited number of enterprise or project
resources as well as plan these resources
in the Gantt diagram. You can enter actual
time used for each resource which, if you
do so, automatically appears into the
time reports.