Project Management Console (Task Remaining Hours)

 

In the project console you can adjust the remaining hours for each individual task based on the remaining hours entered by the resources when timesheets are submitted.  You have the option of accepting the remaining hours submitted by the resources, or you can override the remaining hours with your own estimation.  The remaining hours set in the project console becomes the basis for the Project Overview report which is the report that tells you if your project is ahead behind schedule and by how much.

 

The project manager (if you have the Approval Management module) or whoever you assign to be in charge of the project if you do not had that module, should go to this page on a daily basis and update the remaining hours so that the Project Overview report always is up-to-date.

 

In 3f Project 2006 a task is consider finished when the remaining hours = 0. This is where you sit tasks to finished by simply adjusting the remaining hours for the task that is finished to = 0.

 

Why are the remaining hours not set automatically when timesheets are submitted?

The reason is that it will not be accurate enough.  When a resource submits his or her timesheet the remaining hours entered can only be the resources best guess or estimation.  The individual resources working on a project may not always have the information needed to properly estimate the remaining hours on a task for themselves, and even less so if multiple resources are working on the same task. Therefore by forcing the project manager or the person is in charge of the project to review the remaining hours for all the tasks on a daily basis will not only increase the accuracy of the Project Overview report, but would also alert him or her to problems earlier if the remaining hours suddenly and unexpectedly begins to increase.

As mentioned above, the way a task is set to finished is by adjusting the remaining hours for the task to 0. In 3f Project 2006 deciding when a task is finished is the job of the project manager.

 

The image below shows the project console, and as you can see the column "Rem. Hrs" has entry fields.  To adjust the remaining hours by task all you have to do is to changes the hours in this field across from the task you want to adjust.  If you want to accept the sum of all the remaining hours entered by the resources working on the task you can click the button Set Task to the right of that field. Finally, if you want to see the remaining hours entered by the resources, you must click the link to the immediate right of the Set Task button.  Doing so opens up a new form with a breakdown. In addition, you can also cancel tasks, change activity and view the task detail.

 

 